Skip to main content

The Killanoola Oil Project is Red Sky’s 100% owned Flagship located in South Australia’s onshore Otway Basin. It was acquired in February 2021 from Beach Energy. PRL-13 covers an area of 17.5 sq km and is located in southeastern South Australia close to the Jacaranda Ridge and Haselgrove Gas Fields and Katnook Gas Processing Facility in the Penola Trough of the onshore Otway Basin.

The Killanoola oilfield was discovered by the Killanoola-1 well in 1998 at a depth of 850 metres. The oil is a 34° API waxy crude. Previous flow tests of the well have recorded rates of up to 300 barrels of oil per day.

An independent petrophysical report commissioned by Red Sky on the Killanoola-1DW-1 well identified potentially 37 metres of additional oil bearing pay zones within the 149-metre-thick Sawpit Sandstone. This evaluation adds significantly to the currently perforated pay zone of 5 metres. Future geological and geophysical studies will integrate these findings into new reservoir and structure models.

These results follow the exceptional result of 16m of Net Pay for the Killanoola SE-1 well which was in stark contrast to the previous net pay estimates of 1.5m. Killanoola SE-1 was drilled in 2011 and also discovered oil. This well has not undergone a production test.

Recent Developments

In August 2023, Red Sky finalised an agreement with Viva Energy Australia Pty Ltd (ASX:VEA) to purchase all crude from the Killanoola oil field project, subject to required quality specifications. Delivery will be made to Viva Energy’s Geelong refinery by road tanker, approximately four hours southeast of the project site.

In December, works to prepare the well for the extended production test commenced after Red Sky received approval from the Government of South Australia (SA) Department for Energy and Mining (DEM), and contractors were mobilised to the site.

However, operations at the DW1 well were suspended shortly after due to a downhole mechanical failure of the existing pump, which led to the well losing its capacity to lift fluid to the surface. Operations were halted pending the installation of a new pump, which will be part of the 2024 work programme.

Despite encountering mechanical issues, initial flow rates were promising. An initial rate of 62 bbl/day, on an increasing trend, was observed.

Initial plans were to contract a drilling rig for workover and drilling operations in 2024. The focus was to drill two new wells and perform a workover, including relocating one well based on seismic data interpretation and replacing the faulty pump.

Killanoola Forward Plan

The forward programme at Killanoola has been further revised as announced in May 2024. Initially, plans to replace the faulty pump at the DW1 well using a crane were reassessed due to potential well control risks and marginal cost savings. Instead, we have opted for a more conventional approach using a concentric workover unit, which will prove more cost effective and is expected to enhance operational efficiency and safety. An Activity Notification (AN) has been lodged with the Department for Energy and Mining (DEM) for this operation.

Additionally, the forward program for the KN2 and SE2 wells has been revised due to cost inflation associated with building new well pads and ongoing costs. Red Sky is now evaluating drilling these additional wells from the existing well pads at K1 DW1 and SE1 as deviated wells. This approach will significantly reduce costs and logistical challenges. Drilling from existing well pads also allows us to leverage existing infrastructure, thus avoiding the high expenses and complexities of constructing new well pads and ongoing costs from new lease agreements.

Discussions are ongoing to support the revised drilling plans regarding securing condensate supply for blending to ensure flow assurance and buyers for the crude. These discussions are crucial for optimising the production process and maintaining steady output. By drilling from existing well pads, we not only cut costs but also expedite the process. The SE2 site requires a deviation of 270 metres, and the KN2 site requires 470 metres, which are within industry standards.

The Company continues to engage with the DEM to secure the necessary approvals. Our revised approach aligns with our broader strategy to optimise resource utilisation, reduce operational risks, and enhance shareholder value through careful and calculated project management.

Highlights

  • Red Sky acquired Killanoola Oil field (PRL-13) from Beach Energy
  • 100% owned Flagship Project located in South Australia’s onshore Otway Basin
  • Killanoola passed through at least four operators since discovery, severely disrupting development
  • An updated Independent Report on the Discovered PIIP was completed in April 2023
  • Best Estimate PIIP now calculated at 135.5 mmbbls, a 45.7% increase from previous March 2022 Best Estimate PIIP
  • Red Sky is targeting 30 mmbbls plus oil recoverable
  • Sale agreement signed with Viva Energy (ASX:VEA) in August 2023 for all crude produced subject to specifications, benchmarked against dated Brent for pricing
  • SA DEM approval received to commence production at Killanoola DW1

Field History

  • PRL-13 covers an area of 17.5 km2 and is located near the Haselgrove and Jacaranda Ridge gas fields and approximately 25 km NW of the Katnook gas fields and processing facility.
  • In 1998, the Killanoola oil field was discovered by the Killanoola-1 well at a depth of 850 metres.
  • Discovery well was deviated to an up-dip position by the Killanoola-1 DW-1 well and a drill stem test produced about 120 bopd.
  • A second well Killanoola SE-1 was drilled in 2011 but no production test was carried out.
  • 5m of net pay was perforated in the side track, Killanoola-1 DW-1, and it was cased and suspended as an oil well on 2 May 1998.
  • The licence also includes an additional untested fault closure, called Killanoola South. This fault block is considered a success in the high case.
  • Reserves Summary from Previous Operators:
    • Beach Energy estimated reserves at: P90=500,000 bbls / P50=2,900,000 bbls / P10=6,700,000 bbls
    • Essential Petroleum (EPR) stated: 7 million bbls in place / 800,000 bbls recoverable (only 14%)

Recent developments include:

  • In December 2021, a successful oil sampling operation was carried out at Killanoola-1 DW-1.
  • The collected samples were sent to the Intertek laboratory for assay studies.
  • Results indicated that the Killanoola crude is ideal for producing gasoil. The maximum pour point is 36 degrees Celsius which is indicative of a highly waxy crude, and the API density is 36.7.
  • This waxy crude would require heating up throughout the production process: flowlines, separator, storage tank and possibly trucking.
  • In May 2022, the Killanoola Project discovered PIIP was revised upward from 7 mmbbls to 93 mmbbls Best Estimate, representing a 1228% increase.
  • Upon completion of the interpretation of the 3D seismic, which was acquired and processed in 2022, Red Sky commissioned a further updated report from Global Resources & Infrastructure Pty Ltd (GRI) on the PIIP.
  • Interpretation of the new 3D seismic data resulted in changes to the size of the structural compartments.
  • Red Sky is targeting 30 mmbbls plus oil recoverable.
Killanoola Oil Field Discovered Petroleum Initially in Place (mmbbls)
  Low Best High
9-Apr-21 2 7 13.8
31-Mar-22 57.2 93 98.6
19-Apr-23 28.9 135.5 157.4

Table 1: Summary Discovered Petroleum Initially In Place (PIIP) Killanoola Oil Field

PRL 13 Potential

Killanoola-1 Block (1 in map)
  • Killanoola-1 DW1: can be brought back into production quickly
  • Red Sky plans to use a proven additive for flow assurance
  • New pay zones identified by petrophysical interpretation
  • Improved flow rates are expected from the well once the new pay zones are perforated
Killanoola South Block (2 in map)
  • The Killanoola South block is untested and has the same geological setting as Killanoola-1 DW1 and SE-1
  • Red Sky proposes to drill this prospect
Killanoola Southeast Block (3 in map)
  • Killanoola SE-1 well discovered oil in 2011 and is suspended awaiting commercial testing
1
Killanoola-1 Block
2
Killanoola South Block
3
Killanoola Southeast Block

Near Top Reservoir Depth Map